build program
On this page we aim to record the progress of the building phase.
The building plan consists of 2 phases that run in parallel: the External Groundworks and the Community Centre Building. The key elements of the plan are as follows:
|
Activity |
Target completion date
|
| External Groundworks | |
|
site set up/publicity pictures |
Tue 10/11/09 |
|
herass fence to perimeter |
Tue 10/11/09 |
|
site signage |
Mon 09/11/09 |
|
engineer datum points |
Tue 10/11/09 |
|
temporary access |
Fri 13/11/09 |
|
site office/welfare unit delivery |
Thu 12/11/09 |
|
temporary electric supply |
Fri 11/12/09 |
|
strip site |
Fri 13/11/09 |
|
cut off drain behind hall |
Fri 20/11/09 |
|
breakrock hall foot print |
Fri 27/11/09 |
|
excavate foundations |
Fri 04/12/09 |
|
foul water service |
Fri 18/12/09 |
|
water/BT service |
Wed 20/01/10 |
|
sewerage package pump |
Fri 18/12/09 |
|
fencing |
Wed 03/02/10 |
|
manholes |
Mon 11/01/10 |
|
drainage |
Tue 09/02/10 |
|
access road formation |
Fri 18/12/09 |
|
reduce levels/break rock |
Mon 11/01/10 |
|
proccess rock |
Tue 19/01/10 |
|
place+compact rock |
Fri 29/01/10 |
|
car parks formation |
Fri 12/02/10 |
|
concrete foundations kerbs |
Fri 26/02/10 |
|
form open ditches/batters |
Tue 09/03/10 |
|
gulleys |
Thu 11/03/10 |
|
kerbing |
Thu 25/03/10 |
|
surface water drainage |
Thu 08/04/10 |
|
type 1 road/carpark |
Thu 15/04/10 |
|
paving |
Mon 26/04/10 |
|
grasscrete |
Wed 05/05/10 |
|
path formation |
Wed 12/05/10 |
|
heel kerbs |
Wed 19/05/10 |
|
landscaping |
Thu 10/06/10 |
|
tar base coarse |
Fri 04/06/10 |
|
tar wearing course |
Fri 10/09/10 |
|
Community Centre |
|
|
concrete foundations |
Tue 22/12/09 |
|
erect steel frame |
Fri 22/01/10 |
|
roof cladding |
Mon 01/02/10 |
|
blockwork to FFL |
Wed 03/02/10 |
|
rain water goods |
Fri 05/02/10 |
|
concrete floor slab |
Fri 12/02/10 |
|
fabricate timber frame |
Fri 26/02/10 |
|
erect timber frame |
Fri 19/03/10 |
|
windows/doors |
Fri 02/04/10 |
|
blockwork/cills+lintels |
Fri 07/05/10 |
|
render |
Thu 20/05/10 |
|
fabricate internal partitions |
Fri 16/04/10 |
|
erect internal partitions |
Fri 07/05/10 |
|
electric 1st fix |
Fri 04/06/10 |
|
fire alarm 1st fix |
Tue 18/05/10 |
|
plumbing first fix |
Fri 11/06/10 |
|
joinery 1st fix 34 |
Thu 24/06/10 |
|
insulation |
Fri 04/06/10 |
|
gyproc sheeting |
Thu 24/06/10 |
|
ames taping |
Fri 16/07/10 |
|
painting under coat |
Wed 21/07/10 |
|
electric 2nd fix |
Fri 15/10/10 |
|
plumbing 2nd fix |
Fri 15/10/10 |
|
joinery 2nd fix |
Thu 14/10/10 |
|
armitage venesta delivery |
Fri 20/08/10 |
|
painting+decorating |
Fri 17/09/10 |
|
fire alarm 2nd fix |
Wed 15/09/10 |
|
floor finishes |
Thu 14/10/10 |
|
kitchens |
Fri 15/10/10 |
|
builders clean |
Thu 21/10/10 |
|
testing + commissioning |
Fri 29/10/10 |
|
disenfecting water service |
Mon 25/10/10 |
|
snagging |
Tue 09/11/10 |
|
Hand-over to client |
Tue 09/11/10 |