On this page we aim to record the progress of the building phase.

The building plan consists of 2 phases that run in parallel: the External Groundworks and the Community Centre Building. The key elements of the plan are as follows:

Activity

Target completion date
External Groundworks  

site set up/publicity pictures

Tue 10/11/09

herass fence to perimeter

Tue 10/11/09

site signage

Mon 09/11/09

engineer datum points

Tue 10/11/09

temporary access

Fri 13/11/09

site office/welfare unit delivery

Thu 12/11/09

temporary electric supply

Fri 11/12/09

strip site

Fri 13/11/09

cut off drain behind hall

Fri 20/11/09

breakrock hall foot print

Fri 27/11/09

excavate foundations

Fri 04/12/09

foul water service

Fri 18/12/09

water/BT service

 Wed 20/01/10

sewerage package pump

Fri 18/12/09

fencing

Wed 03/02/10

manholes

Mon 11/01/10

drainage

Tue 09/02/10

access road formation

Fri 18/12/09

reduce levels/break rock

Mon 11/01/10

proccess rock

Tue 19/01/10

place+compact rock

 Fri 29/01/10

car parks formation

 Fri 12/02/10

concrete foundations kerbs

 Fri 26/02/10

form open ditches/batters

 Tue 09/03/10

gulleys

 Thu 11/03/10

kerbing

 Thu 25/03/10

surface water drainage

 Thu 08/04/10

type 1 road/carpark

 Thu 15/04/10

paving

 Mon 26/04/10

grasscrete

 Wed 05/05/10

path formation

 Wed 12/05/10

heel kerbs

 Wed 19/05/10

landscaping

 Thu 10/06/10

tar base coarse

 Fri 04/06/10

tar wearing course

 Fri 10/09/10

Community Centre

concrete foundations

 Tue 22/12/09

erect steel frame

 Fri 22/01/10

roof cladding

 Mon 01/02/10

blockwork to FFL

 Wed 03/02/10

rain water goods

 Fri 05/02/10

concrete floor slab

 Fri 12/02/10

fabricate timber frame

 Fri 26/02/10

erect timber frame

 Fri 19/03/10

windows/doors

 Fri 02/04/10

blockwork/cills+lintels

 Fri 07/05/10

render

 Thu 20/05/10

fabricate internal partitions

 Fri 16/04/10

erect internal partitions

 Fri 07/05/10

electric 1st fix

 Fri 04/06/10

fire alarm 1st fix

 Tue 18/05/10

plumbing first fix

 Fri 11/06/10

joinery 1st fix 34

 Thu 24/06/10

insulation

 Fri 04/06/10

gyproc sheeting

 Thu 24/06/10

ames taping

 Fri 16/07/10

painting under coat

 Wed 21/07/10

electric 2nd fix

 Fri 15/10/10

plumbing 2nd fix

 Fri 15/10/10

joinery 2nd fix

 Thu 14/10/10

armitage venesta delivery

 Fri 20/08/10

painting+decorating

 Fri 17/09/10

fire alarm 2nd fix

 Wed 15/09/10

floor finishes

 Thu 14/10/10

kitchens

 Fri 15/10/10

builders clean

 Thu 21/10/10

testing + commissioning

 Fri 29/10/10

disenfecting water service

 Mon 25/10/10

snagging

 Tue 09/11/10

Hand-over to client

 Tue 09/11/10